A361 North Devon Link Road

Subcontract Package

Lankey Junction Drainage Installation

Client

Alun Griffiths (Contractors) Ltd.

Location

A361 North Devon

Duration

Circa 15 weeks

Completion Date

Winter 2022

Project Overview

Scope of Works:

  • The drainage element on the conversion of a 3-arm priority junction to a 4-arm roundabout.
  • 7 km of carrier drain, with diameters ranging from 150mm to 600mm
  • 4 km of carrier/filter drain at 225mm diameter
  • 5 km of narrow filter drain
  • Manhole chambers, with diameters ranging from 600mm to 21,500mm
  • Headwalls, with diameters ranging from 150mm to 600mm
  • Flow control chambers in chambers up to 1,500mm diameter.
  • 1km of V-ditch
  • 3km of precast concrete channel