St Marnocks Bay

  Location Portmarnock, Ireland Duration 24 Months Completion Date Sept, 2022 Project Overview Scope: Full Groundworks Package for over 153 units Excavation of Roads Capping and Sub-base Installation of in-situ kerbs approx.6 km Blacktop to all road networks Base, Binder, and Wearing Course to complete road network Installation of all mainline foul and storm drainage […]

Bellmayne Residential Development

Location Sisk Duration 9 Months Completion Date May 2024 Project Overview Subcontract Scope: Site Development Infrastructure incl all services, paths and haul roads. Bulk excavation & removal off site Foundation prep and blinding. Stormwater and foul drainage system. Excavate, bed, lay, backfill and test 4,000m of pipework incl over 30 precast manholes. 3,3000 m of […]