hartecivil

Project Overview

Scope of Works:

  • 5 km of carrier drain, with diameters ranging from 225mm to 900mm
  • 5 km of filter drain, with diameters ranging from 225mm to 600mm
  • 5 km of narrow filter drain
  • Manhole chambers, with diameters ranging from 1,050mm to 2,100mm
  • Headwalls, with diameters ranging from 300mm to 900mm
  • Flow control chambers in chambers up to 2,100mm diameter.

Client:

  • Subcontract Package:   Drainage Installation Package 3
  •                               
  • Client:   FCC Construcción S.A. UK Branch

Latest Projects

Civil

SEGRO Logistics Park Northampton Gateway

SEGRO Logistics Park Northampton Gateway Project Overview Scope of Works: headwalls chambers & catchpits (1050 -1500mm dia.), including Hydrobreaks and orifices plates gullies, including concrete

Civil

A361 North Devon Link Road

A361 North Devon Link Road Project Overview Scope of Works: The drainage element on the conversion of a 3-arm priority junction to a 4-arm roundabout.

Commercial

Lyreen Meadows, Kilcock

Lyreen Meadows, Kilcock Project Overview Scope of Works: Site Development Infrastructure incl all services, paths and haul roads. Excavate, install drainage/ducting, install foundation Pad for

Commercial

Claremont, Howth Rd

Claremont, Howth Rd Project Overview Scope of Works: Site Development Infrastructure incl all services, paths and haul roads. Crop & prep 650 piled pad foundations

Commercial

Centre for Future Learning, UCD Campus

Centre for Future Learning, UCD Campus, Project Overview Scope of Works: Site Development Infrastructure incl all services, paths and haul roads. Demolition and removal of

Residential

Bellmayne

Bellmayne Project Overview Scope of Works : Site Development Infrastructure incl all services, paths and haul roads. Bulk excavation & removal off site Foundation prep

Civil

ABBVIE Trinity BT Pharmaceutical Sligo

ABBVIE Trinity BT Pharmaceutical Sligo Project Overview Scope of Works: Cofferdams Drainage Ducting Client: John Paul Construction Sligo Ireland 6 Months March 2019 Project Gallery